No Damages for Delay Clauses Mean What They Say

» Articles » Construction Articles » Article

October 10, 2007


Delays on a public works project are the bane of many contractors' existence in a project for a public entity. That's because the contracts for such projects often contain a "no damages for delay" clause.

Even though the strict application of such clauses can be unfair, a recent ruling by the Ohio Supreme Court makes clear that they will be enforced anyway if the provisions are plainly worded.

In the Ohio case, the lead contractor on a building construction project on the Ohio State University campus filed suit to recover $3,400,000 in damages arising from delays in the project. The contractor claimed that the delays resulted from inaccurate and incomplete design plans and specifications. By all accounts, it appears that the plans and specifications were incomplete and were repeatedly changed during the project. Adding insult to injury, however, Ohio State not only refused to pay for the delay damages, it also deducted liquidated damages from the lead contractor's proceeds because of the delay in completion of the project. The court determined that because of the "no damages for delay" clause in the contract, the contractor's only remedy was to seek more time in which to complete the project.

The contractor argued that the Spearin doctrine — which permits recovery of damages in a public works project where the public owner makes affirmative representations regarding project site conditions — should apply. The Ohio Supreme Court disagreed.

Continue reading below

FREE Construction Training from Lorman

Lorman has over 38 years of professional training experience.
Join us for a special white paper and level up your Construction knowledge!

Best Practices for Measuring and Documenting Construction Delays

Learn More

The lesson here is that, if the courts and the government won't look out for a contractor, then the contractor needs to look out for itself. A contractor's bid should factor in at least some risk contingencies for delays that arise through no fault of its own. If not, a contractor can win the contract bid, but lose its shirt.

Citation for lawyers: Dugan & Meyers Constr. Co. Inc. v. Ohio Dep't of Admin. Services, 864 N.E.2d 68 (Ohio App. 2007).


The material appearing in this web site is for informational purposes only and is not legal advice. Transmission of this information is not intended to create, and receipt does not constitute, an attorney-client relationship. The information provided herein is intended only as general information which may or may not reflect the most current developments. Although these materials may be prepared by professionals, they should not be used as a substitute for professional services. If legal or other professional advice is required, the services of a professional should be sought.

The opinions or viewpoints expressed herein do not necessarily reflect those of Lorman Education Services. All materials and content were prepared by persons and/or entities other than Lorman Education Services, and said other persons and/or entities are solely responsible for their content.

Any links to other web sites are not intended to be referrals or endorsements of these sites. The links provided are maintained by the respective organizations, and they are solely responsible for the content of their own sites.