Public works projects typically contain many tiers of parties. The owner contracts with the general contractor, which contracts with a subcontractor, which contracts with a subsubcontractor, which contracts with a supplier, which contracts with a manufacturer. If a construction company goes bankrupt or becomes insolvent, those impacts can be felt across several tiers.

A recent case before the Indiana Supreme Court makes clear that lower tiered parties have less rights the farther they get contractually from the owner and general contractor. In this case, the third-tier subcontractor, who manufactured prefabricated bridge components, failed to get paid by a second-tier subcontractor on the redesign and reconstruction of a bridge. The manufacturer then submitted a claim on the performance bond that had been posted pursuant to Indiana's statutory requirement for public works projects. The court ruled that the rights to recover against this bond did not extend beyond parties who have a contract with either a first-tier subcontractor or the general contractor. The court concluded that the statutory language requiring bonds was not meant to cover lower tier claims and that courts could not extend that coverage - only the legislature can do that by changing the law.

Given the corresponding limitations in public works projects that prevent contractors from exercising rights and tools like mechanics' liens, this ruling can have devastating consequences for lower tier contractors and suppliers. To protect itself from these risks, a lower tier contractor in a public works project needs to carefully document its dealings with public works subcontractors and to provide for being paid contemporaneously (or nearly so) with the delivery of goods and services. Otherwise, the lower tier carrier can deliver goods and services in a public works project and still be left holding an empty bag when it is time to be paid.

Citation for lawyers: Alberici Constructors, Inc. v. Ohio Farmers Ins. Co., 866 N.E.2d 740 (Ind. 2007).


The material appearing in this web site is for informational purposes only and is not legal advice. Transmission of this information is not intended to create, and receipt does not constitute, an attorney-client relationship. The information provided herein is intended only as general information which may or may not reflect the most current developments. Although these materials may be prepared by professionals, they should not be used as a substitute for professional services. If legal or other professional advice is required, the services of a professional should be sought.

The opinions or viewpoints expressed herein do not necessarily reflect those of Lorman Education Services. All materials and content were prepared by persons and/or entities other than Lorman Education Services, and said other persons and/or entities are solely responsible for their content.

Any links to other web sites are not intended to be referrals or endorsements of these sites. The links provided are maintained by the respective organizations, and they are solely responsible for the content of their own sites.